Iteration 1
RSF port, deeper gradebook integration, minimal functionality
- Completed in January, 2008
Iteration 2
Parity with legacy assignments tool functionality, site-to-site import for migration, but without significant design changes
- Feature Freeze March 7, 2008.
- QA through April 11
Iteration 3
Refinement for Production
- Design completed by April 11, 2008
- Production deployment at IU June 21
Iteration 4
Final cleanup of Iteration 3 design
- whatever polish needs to be applied between June and August
Iteration 5
Redesign of User Experience
- Using a JSON approach for rapid UI development
- UX goals: simplicity of screens, clarity of workflow, design for large class tasks as well as small
- Will work through several iterations of usability testing in May
- Targeting deployment at Georgia Tech in August
|
Deployment at IU
- Iteration 3 to be piloted in June, 2008
- Full production in August
Deployment at Georgia Tech
- Iteration 5 to be piloted in July, 2008
- Full production in August
|